Wall-Mount Bracket Installation

Determine the location where the base bracket will be
installed.

(1) Use tape or other means to mark the measured positions

on the wall where the display will be installed. The center
of the “X” drawn from the four corners of the square marks
the center of the panel.

(2) Take the coin with the string and align it perpendicular to

the base bracket.
Use a pencil, etc., to mark the two screw hole locations.

Cellophane tape, etc.

Wall-mount bracket
unit installation hooks

Position the base
bracket so that the
perpendicular parts
of it are parallel with
the string.

Position the base
bracket so that the
center of it is aligned
with the string.

Use a pencil, etc., to
mark the screw hole
position on the wall
behind the bracket.

923mm

1572mm

Display
outline

Dimension lines
used as a guide

Base
bracket
outline

Cellophane tape, etc.

String

Weight

Center
line

shaped screw holes

Tighten the screws

Temporarily remove the base bracket from the wall and loosely screw in off-the-shelf screws (8

mm dia.

× 2 screws) in the screw hole positions marked on the wall. At this time, the screw

heads should extend more than 4 mm above the wall so that the base bracket can be hung on

the screw heads. Hang the base bracket on the installed screws, check to make sure the

bracket is not sagging to the left or right, and then firmly tighten the screws. Use off-the-shelf

screws to secure the remaining screw holes (15 screws). (The screw hole diameter is 9 mm.)

Min. 4mm

Use the weight with the string
used in Step 1 to make sure
the bracket is perpendicular.

*When marking on the wall, use a material that will not leave a permanent mark on

the wall and get the approval of the customer before beginning the work.