BURNER SETUP & BOILER OPERATION

A. BURNER INSTALLATION

1. The oil burner is supplied with a mounting flange

fixed in position.

2. Mount the burner to the burner mounting plate (item

5) with four (4) 5/16" studs and nuts provided.

3. Care must be taken when routing the oil lines so not

to interfere with the opening and closing of the
burner mounting plate. Flexible oil lines or flared
copper disconnects with valves (when copper lines
are used) may be installed to assure full opening of
the burner mounting plate when servicing.

4. Oil burner specifications:

For information pertinent to the oil burner such as
nozzle sizing, fuel supply piping, adjusting or
servicing, refer to the charts in this section and the
burner installation manual.

B. BURNER START-UP AND ADJUSTMENT

1. Burner should start automatically when thermostat is

turned up and main boiler service switch is turned
on. If burner does not start, check to be sure there is
oil in the tank and push reset button on burner
control:

Beckett: Square red button.

Carlin: Round red button.

Riello: Round red button inside clear flexible

cover on back of burner cover.

If burner still does not start, contact serviceman.

2. Adjust burner and barometric draft control for

highest CO² (Maximum 13%) while maintaining a 0

Smoke and -.01 to -.02" W.C. draft overfire.

All adjustments must be made using suitable
instruments such as found in a Bacharach
Combustion Test Kit.

3. Burner and boiler can be shut down by turning

down the thermostat and moving the main boiler
service switch to the "off" position.

4. See burner manufacturer’s manual for further

information regarding the burner.

C. CHECK BOILER CONTROLS

1. Limit and Operating Controls:

a. Lower the set point of each control until the

burner shuts down. Note that the system pressure
(or temperature) corresponds to the desired set
point.

b. Return the controls to the desired set point.

2. Low Water Cut-off (if used) - consult the

manufacturer's instructions for the low water cut-off
operational check procedure.

D. PURGE AIR FROM THE SYSTEM

(WATER BOILERS ONLY)

1. Purge the system using purge valves, isolating zones

in the process or use system vents. Do not operate
the pump(s) while purging. Pumps will hold air in
the eye of the impeller.

2. Allow the system to reach 180°F and use manual

vents, if installed, to remove any remaining air.
Watch the pressure gauge as the system approaches
180°F. If the pressure exceeds the design operating
pressure, check:

a. Fill valve pressure.

b. Expansion or compression tank operation and

sizing.

5. BURNER SETUP & BOILER OPERATION

Burn only #2 Fuel Oil in this
appliance. Do not use gasoline,
crankcase drainings or any oil
containing gasoline.

CAUTION

Do not attempt to start the burner
when excess oil has accumulated,
when the unit is full of vapor, or
when the combustion chamber is
very hot.

CAUTION

Two-pipe oil supply for Riello burner
requires a separate kit. Order part
#C7001026 from Riello dealer.

NOTICE

Be sure high temperature gasket is
between the burner mounting flange
and the burner mounting plate.

NOTICE

Do not start the burner unless all
cleanout doors are in place.

CAUTION