Figure 3-8



Another way is to install your crane system is to first assemble the crane on the floor

beneath the runway/rails. Then lift the crane into position as shown in Figure 3-9.

Travel Rail

Figure 3-9



When installing the hoist and trolley on the bridge beam, refer to the installation

instructions for your hoist and trolley.

3.3

Max-E-Lift End Trucks

(for Double Girder Crane Systems)

3.3.1

Assemble and install the Max E Lift cranes using the appropriate information in section 3.1 or 3.2
based on whether your Max E Lift system is underhung or top running.

3.3.2

Refer to Figure 3-10 and verify the following:

a) End Truck Alignment - verify A = B and X = Y.