4.6.2. Measurement procedure for "3P" test mode
The measurement is taken according to what prescribed for CEI 64.8, IEC 781, VDE 0413,
EN61557-5.

1. Select "

3P" earth measurement mode by means of the F1 key.

2. Connect the Black, Red, Green and Blue cables to the corresponding input terminals of the

instrument

B1, B2, B3, B4 (see possible connections in the following picture).

3. Connect the black, and green cables to the earth plant and red and blue cables to the

auxiliary rods.

B2

B3

B4

B1

3 points earth resistance measurement


Measuring small earth plants, current probe must be positioned a distance from the earth
equipment outline corresponding to five times the diagonal of the area of the earth
equipment under test, measuring big earth plants this distance could be reduced up to one
time the diagonal.


4. Press

the

START/STOP key. The instrument starts the test.


At the end of the test the instrument

displays the values alongside.

EARTH

0.96

2P 0.93 Ω


CAUTION

The display of

“Measuring” means that the instrument is measuring. During

this phase never disconnect test leads.


SAVING:

The tests can be stored pressing the

SAVE key twice

(according to paragraph 5.1).


START

STOP

Mode “2P”.

Measured
resistance value

Average value of earth resistance calculated over
the number of test displayed.

SAVE