Shimming procedures – Lull 1044C-54 Series II Service Manual User Manual

Page 190

Advertising
background image

Boom and Transfer

6-48

31200079

Shimming Procedures

4-Section Boom

Fig. 6-45: Boom Slide Pad Locations – 4-Section Boom

1. Park machine on firm, level surface and apply park brake. Level the

frame. Level and fully retract the boom. Shut off engine.

2. Determine if all boom slide pads are serviceable. (See “Slide Pad

Inspection” on page 6-34). Have replacement pads ready as required.

Fig. 6-46: Boom Section Gaps – Front of 4-Section Boom

0

80

60

40

20

-20

0

80

60

40

20

-20

J

1160

1

1

3

1

1

1

2

2

2

2

2

2

2

2

2

2

2

2

NOTE: Items 1 and 3 are load bearing pads

2

#

Description

1

Boom Pad, 1" Thick x 3" Wide

2

Boom Pad, 9/16" Thick x 2" Wide

3

Boom Pad, 3/4" Thick x 3" Wide

#

Description

4

Boom Pad, 3/4" Thick x 1-1/4"
Wide

4

J

1161

0.75"–1.00"

0.67"–0.82"

0.62"–0.74"

(5/8"–3/4")

(3/4"–1")

(11/16"–13/16")