Boom and Transfer

6-62

31200079

installation

4-Section Boom

1. Prepare replacement boom for installation by removing strapping and

blocks used for shipment. Note location of straps and blocks for use on
the previously removed boom.

2. With the replacement boom still lying upside down, the front carriage

tilt cylinder should be installed at this point. It is easier to install when
the boom is in this position. See page 6-20

3. Attach slings/chains to the boom and crane. Lift the boom and rotate it

to the upright position.

4. Position the boom over the transfer carriage/boom cradle. Carefully

lower boom and align boom pivot boss with the matching bosses in the
transfer carriage/boom cradle.

5. (Ref. Fig. 6-66) Partially insert two (2) boom pivot pins to temporarily

secure the boom pivot. Check gaps between boom pivot boss and the
matching bosses in the transfer carriage/boom cradle. Select
appropriate shim sizes to center the boom in the transfer
carriage/boom cradle.

6. (Ref. Fig. 6-66) Slide the boom pivot pins out one at a time and insert

the required shims. Fully insert the boom pivot pins.

7. (Ref. Fig. 6-61) Align rod-end of a boom hoist cylinder with the

matching boss on the boom. Insert pivot pin and secure with lock pin,
lockwasher, and capscrew. Repeat this procedure for the other hoist
cylinder and rear carriage tilt cylinders.

8. The slings/chains and crane may be removed at this point.

9. (Ref. Fig. 6-61) Connect the two (2) auxiliary hydraulic hoses and two

(2) carriage tilt hoses to the rear of the boom.

10. Connect the two (2) hoses to the boom extension cylinder lines.

11. Lubricate all pivot grease fittings with EP lithium based grease.

12. Install boom extension proximity switch. See Step 9 on page 6-128.

13. Install boom elevation proximity switch in transfer carriage/boom

cradle. See “Boom Elevation Proximity Switch” in Section 7.

14. Install quick attach assembly to boom. See page 6-45.

15. (Ref. Fig. 6-66) Start engine and extend the boom approximately eight

inches. Shut engine off. Secure pivot pins with two (2) capscrews,
lockwashers, and nuts. Torque nuts to 110 ft-lbs.

16. Start engine and cycle the frame tilt fully several times.

a. Raise the boom, noting that Rear Osc Lock light illuminates when

boom is at about 40° elevation. If light does not illuminate, stop and
lower the boom. Follow procedures for under “Boom Elevation
Proximity Switch” in Section 7.

b. Complete proximity switch adjustment before proceeding to

Step 17.

17. Cycle all boom hydraulics several times to remove air from system.