Transporting a load, Leveling procedure, Transporting a load -6 leveling procedure -6 – Lull 944E-42 Operation Manual User Manual

Page 66

Advertising
background image

Section 4 - Operation

4-6

31200354

Transporting a Load

After engaging the load and resting it against the backrest, tilt the load back to
position it for travel and fully retract transfer carriage. Travel in accordance with the
requirements set forth in Section 1 - General Safety Practices and Section
5 - Attachments.

Leveling Procedure

1. Position machine in best location to lift or place load.

2. Apply parking brake and move transmission control lever to NEUTRAL.

3. Observe level indicator to determine whether machine must be leveled prior to

lifting load. Level machine with frame level joystick (see page 3-16).

4. Move boom/attachment to 4 ft (1,2 m) off ground.

(AUS - Move boom so forks are no more than 11.8 in (300 mm) above ground
surface.)

Important things to remember:

• Never raise the boom/attachment more than 4 ft (1,2 m) above ground unless

telehandler is level.
(AUS - Never raise the forks more than 11.8 in (300 mm) above ground surface
unless telehandler is level.)

• The combination of frame leveling and load could cause the telehandler to tip

over.

OW0540

Advertising
This manual is related to the following products: