SECTION 3 - SERVICE - ELECTRIC POWERED BOOM LIFTS

3-6

– JLG Lift –

3124287

8. Install the Shear Beam Load Cell Connections.

Locate the connector from the Rear-Right Shear
Beam Load Cell (orientation from the normal opera-
tor’s position while using platform control console).
Install the Rear-Right connector into the LSS Mod-
ule’s J8 by carefully rotating the molded portion of
the connector until the keys align, and then tighten-
ing the knurled barrel. Tighten it first by hand (avoid
cross-threading), and then carefully secure it with a
small pair of locking pliers. The connector must be
secured in this fashion to compress its O-ring seal
and assure moisture resistance, but must not be
over-tightened such that it damages the LSS Mod-
ule. Install the Rear-Left into J7, the Front-Right into
J6, and the Front-Left into J5. Neatly bundle the
excess wire using wire ties so it can be stowed in the
region below the LSS Module mounting location.
Ensure that the excess wire length stays within the
platform envelope and does not interfere with
hydraulic hose movement at the rotator.

9. Wire the Load Sensing System to the Host Control

System. Ensure that the Host Control System is
powered-down by depressing the EMS at the
Ground Control station. From the wire harness pro-
vided, insert the Black 12-position Deutsch connec-
tor into J2 on the LSS Module (System Interface –
Communication) to install the JLG Analyzer connec-
tion. Plug the Deutsch connector into J1 on the LSS
Module (System Interface – Power & Digital).

Install a strain relief connector into the platform box
and route the harness from the Grey 12-position
Deutsch connector into the Platform Console Box.

Route the wires under the module. Terminate the
three harness wires inside the Platform Console Box
according to the Wiring Diagram for the Load Sens-
ing System. Match the wire colors and numbers
from the LSS harness to those of the Host Control
System.

10. Setup the Host Control System to enable the Load

Sensing System. Power-up the Host Control System
by resetting the EMS at the Ground Control station.
Plug the JLG Analyzer into the Host Control Sys-
tem’s Analyzer Connection at the Ground or Plat-