48. Four-port and early five-port; Install new O-ring (B)
on plug (A). Install check ball (C). Be sure check ball is
seated in bottom of hole. Install plug. Do not tighten.

Five-Port Shown

M43832

-UN

-08JAN90

NOTE: Four-port not shown. Unit is similar to early

five-port.

49. Later five-port; Install check ball (E) in countersunk
hole (hole closest to the center of the port manifold).

50. Apply petroleum jelly on new O-rings (A) and new
seal ring (B). Install O-rings and seal ring in port cover.

IMPORTANT: Align grooves (C) in port cover with

grooves (D) in manifold.

51. Install port cover with seals toward port manifold.

Early Five-Port

A—O-Ring(s)
B—Seal Ring
C—Port Cover Alignment Grooves
D—Port Manifold Alignment Grooves
E—Check Ball (Later Five-Port)

Later Five-Port

M43843

-UN

-08JAN90

M78055

-UN

-06MAR95

52. Install and tighten four nuts in the sequence shown.
Tighten in several steps to 30 N·m (22 lb-ft).

Early Five-Port Shown

M43845

-UN

-11NOV89

MX,15906006,52 -19-10MAR95

MX,15906006,53 -19-29MAR95

MX,15906006,54 -19-10MAR95

Steering—318 and 420/Steering Valve

TM1590 (17MAY95)

60-06-20

316, 318 & 420 Lawn and Garden Tractors

020895

60

06

20

Advertising
This manual is related to the following products:

316, 420