Installation tasks – Dell POWEREDGE 2950 User Manual
Page 10
8
Rack Installation Guide
Figure 1-1.
Rack Kit Contents
Installation Tasks
Installing a rack kit involves performing the following tasks (described in detail in subsequent sections)
in their numbered order:
1 Removing the rack doors
2 Marking the rack
3 Configuring the sliding rail assemblies
4 Installing the mounting rails in the rack
•
RapidRails installation
•
VersaRails installation
5 Installing the system in the rack
6 Installing the cable-management arm
7 Routing cables
8 Attaching the cable-management arm ramp assembly
9 Replacing the rack doors
1
cable-management arm
2
left cable-management arm
ramp assembly
3
right cable-management arm
ramp assembly
4
slide assemblies
5
10-32 x 0.5-inch flange-head
Phillips screws (8)
6
status indicator cable
(if applicable)
5
1
6
4
2
3