OPERATION AND INSTALLATION MANUAL

Page 5

Site Preparation

All mounting surfaces for the base and loading
plate must be level. The distance between the
mounting surface of the loading plate and base
must be within 1/32” of the nominal height, “H”.
The Load Point Assemblies in a system must be

level to within +/- 0.5

o

.

When mounting the base plate on concrete, use
grout to level the plate.

Do any welding before installing the load points.

Provide proper drainage to prevent the load point
assembly from standing in water.

Precautions

Always treat the Load Sensor as a precision
instrument. Leave the load point assembly in its
packaging until it is time for installation.

NEVER CARRY OR SWING THE LOAD SEN-
SORS BY THEIR CABLES.

Never allow moisture to get into any interconnec-
tions.

HARDY SOLUTIONS RECOMMENDS THAT
YOU DO NOT CUT YOUR ADVANTAGE

®

OR ADVANTAGE LITE® LOAD SEN-
SOR CABLE. BECAUSE YOUR C2®
ACCURACY WILL BE AFFECTED AND
THE WARRANTY VOIDED.

Basic Engineering
Principles for Positioning
Load Point Assemblies

Principle #1

Position the Load Points Assemblies so that the
load (weight) is distributed as evenly as possible
between each load point assembly in the scale.

When the installation does not allow even distri-
bution of the load, select higher capacity load
point assemblies.

NOTE:

All load point assemblies must have the same capacity
when used in one scale.