AAF FLATBANK SIDE ACCESS FILTER HOUSING

INSTALLATION AND OPERATION INSTRUCTIONS

CAUTION…

Review these instructions and all safety procedures with your safety officer.

INSTALLATION OF HOUSING

1. Be sure position of housing access door(s) and direction of airflow

is correct prior to connecting ductwork.

- A minimum of 3 feet clearance is recommended for filter change out -

2. The housing should be permanently connected to the ductwork by

welding, bolting, or riveting. The housing to ductwork connection
should be suitably sealed with caulk or gasket material to
preclude leakage.

3. Following installation of the housing, the system should be

“Vacuumed out” or “Blown-Down” to remove construction dust,
etc., before installing the filters.

INSTALLATION OF FILTERS

1. Leave the filters in the shipping cartons until transported to the

proper housing location. Do not unpack the filters until time of
installation. Unpack the filters taking care not to cause damage.

2. Open the housing access door by unlatching the positive pressure

trip lock latches. The housing door is hinged and can be swung
open completely.

3. There are no locking mechanisms for the filters on the FlatBank

housing.