Cisco CRS-1 User Manual

Page 60

Advertising
background image

A-4

Cisco CRS Carrier Routing System 8-Slot Line Card Chassis Site Planning Guide

OL-5802-09

Appendix A Preliminary Site Survey

Air conditioning

Does the site have the air conditioning
capacity to handle the routing system? If
not, note what will be done to rectify the
lack of adequate cooling.

Describe the air conditioning at the site.

Supported Data Interfaces

Will the routing system be connected to
OC-3/STM-1 POS circuits? How many
ports?

Will the routing system be connected to
OC-48/STM-16 POS or DPT circuits?
How many ports?

Will the routing system be connected to
OC-192/STM-64 POS or RPR XFP
circuits? How many ports?

Will the routing system be connected to
OC-768/STM-256 POS circuits? How
many ports?

Will the routing system be connected to
Gigabit Ethernet (GE) or 10-GE circuits?
How many ports?

Will the routing system be connected to
100-GE circuits? How many ports?

Cable Plant

Have the cables been pulled for all data
interfaces? If not, list the outstanding
cabling that needs to be installed and the
scheduled completion dates.

Are there connection points on the fiber
distribution panel for all optical cables
connecting to the routing system?

Will fiber jumpers be provided? What
length of fiber jumper is required to
complete the installation?

What type of fiber connector is used at the
site?

If attenuation is required, will attenuators
be provided? If not, who will pay for the
attenuators?

Table A-1

Sample Preliminary Site Survey (continued)

Preliminary Site Survey

Advertising