1�- General

In this window,

Figure 46

, enter the following parameters,

Table 8

.

Table 8:Create a new tariff (General)

Parameter

Description

Tariff name

Name of the tariff

Tariff description

(3)

Description of the tariff

Contract types

Drop-down list where the type of contract can be selected:

Flat rate, Contract 1: Flat rate for power

Purchase of units, Contract 2: Purchase of energy units

Purchase of EDA units, Contract 3: Purchase of EDA units

EDA Flat rate, Contract 4: EDA Flat rate

(3)

These fields are not mandatory.

2�- Tariff Costs

The tariff costs and period of time during which they are linked are entered in this window,

Figure 47

.

Figure 47:Create a new tariff (Tariff Costs)

The costs of the tariff depend on the type of contract that has been selected.

Table 9:Create a new tariff (Tariff Costs)

Parameter

Description

Price of energy unit

Cost of the energy unit in €/kWh

Only for Type 2,3 and 4 contracts.

Price of contracted power

Cost of contracted power in €/kW per Day, Week or Month.

(The period of time can be selected)

Net balance fee

An access charge can be applied to customers that have their own

self-powered generators. € per Day, Week or Month.

(The period of time can be selected)