B. Assemble Vent Sections (SLP Pipe Only)

To attach the first vent component to the starting collars

of the appliance:
• Lock the vent components into place by sliding the pipe

section onto the collar.

• Align the seam of the pipe and seam of collar to allow

engagement. Rotate the vent component to lock into

place. Use this procedure for all vent components. See

Figure 10.5.

• Slide the gasket over the first vent section and place it

flush to the appliance. This will prevent cold air infiltra-

tion. High temperature caulk may be used to hold the

part in place.

• Continue adding vent components, locking each

succeeding component into place.

• Ensure that each succeeding vent component is securely

fitted and locked into the preceding component.

Commercial, Multi-family (Multi-level exceeding two sto-

ries), or High-Rise Applications
For Installation into a commercial, multi-family (multi-level

exceeding two stories) or high-rise applications: All outer

pipe joints must be sealed with high temperature silicone,

including the slip section that connects directly to the hori-

zontal termination cap.
• Apply a bead of silicone sealant inside the female outer

pipe joint prior to joining sections. See Figure 10.1.

• Only outer pipes need to be sealed. All unit collar, pipe,

slip section, elbow and cap outer flues shall be sealed

in this manner, unless otherwise stated.

Figure 10.5 Adding Venting Components

WARNING! Risk of Fire or Explosion! DO NOT break

silicone seals on slip sections. Use care when remov-

ing termination cap from slip pipe. If slip section seals

are broken during removal of the termination cap, vent

may leak.

Note: Align seams to engage pipe,

then rotate counterclockwise to lock

C. Assemble Slip Sections

• Slide the inner flue of the slip section into the inner flue

of the pipe section and the outer flue of the slip section

over the outer flue of the pipe section. See Figure 10.6.

• Slide together to the desired length.

Figure 10.6 Slip Section Pilot Holes

Figure 10.7 Screws into Slip Section

Pilot hole

NOTICE: When installing a vent system with an HRC

termination cap, all pipe system joints shall be sealed using

a high temperature silicone sealant.
Apply a bead of silicone sealant inside the female outer

pipe joint prior to joining sections.

Only outer pipes are sealed, sealing the inner flue is not

required.

All unit collar, pipe, slip section, elbow and cap outer

flues shall be sealed.

• Continue adding pipe as necessary following instructions

in “Assembling Pipe Sections.”

NOTICE: If slip section is too long, the inner and outer

flues of the slip section can be cut to the desired length.

• Maintain a 1-1/2 in. (38 mm) overlap between the slip

section and the pipe section.

• Secure the pipe and slip section with two screws no

longer than 1/2 in. (13 mm), using the pilot holes in the

slip section. See Figure 10.7.