Install SpectraLink 6000 System

Survey Site

Check the site to be sure pre-installation work has been completed

correctly. This includes:

Location chosen for the MCU is adequate, and power is available.

Wiring to Base Station locations has been pulled and correctly

terminated.

Phone lines for the SpectraLink 6000 Wireless Telephones are

installed and properly terminated.

Dedicated line is available for remote access to diagnostic modem.

Telephone system administrator is on-site to program the existing

telephone system.

If the work has not been completed, the Polycom field service

engineer can leave the site and reschedule the installation when the

items have been completed or corrected, or assist in preparing the

site.
This unit must be installed by a service person familiar with the

installation of electronic equipment.
Do not power up the unit before it has been properly grounded to a

protective earth. See Grounding instructions below.