Intercooler assembly installation – Banks Power Dodge Trucks: (Diesel ’07 - 12 6.7L Cummins) Intake- Techni-Cooler Charge Air Cooler '07-08 User Manual

Page 5

Advertising
background image

1.

Disconnect the negative battery

cables from both batteries

2.

Disconnect the inlet air

temperature/ pressure sensor

connector located on the air box

cover. the connector is shown in

Figure 2.

3.

Remove the nut that fastens the air

filter housing to the radiator cross brace.

4.

Loosen the hose clamp that

secures the air inlet duct to the

turbocharger inlet. Disconnect the inlet

duct from the turbocharger.

5.

Remove the air box and inlet duct

to turbocharger as an assembly. the

air box is held in place with re-usable

push-in fasteners and can be pulled

out vertically.

6.

Remove the passenger side boost

tube. the boost tubes are the charge

air ducting that route air from the

turbocharger to the charge air cooler

(cac) and from the cac to the intake

manifold.

7.

Remove the driver side boost tube.

Note: Cover the intake manifold and

turbocharger inlet and outlet with a rag

to prevent foreign debris from entering

during installation.

8.

Remove the two upper radiator

attachment bolts.

9.

Remove the two upper cac

attachment bolts.

10.

Remove the 4 bolts (2 per side)

that retain the upper radiator cross

brace, then remove the upper radiator

cross brace. the brace is shown in

Figure 3.

Intercooler Assembly Installation

Figure 2 Location of the Inlet Air Temp/Pressure Sensor

96787 v.4.0

5

Advertising