Chapter 7 Final Checklist Before Energizing
SecureConnect Unit
Checklist
Verify these items before using a SecureConnect unit.
1.
Make sure the stab lockout is pushed in.
2.
Verify the disconnect handle is OFF/O.
3.
Insert the tool in the shaft port and rotate the tool to the right.
The status indicator should change from green to red.
Stab Lockout
Status Port
Shaft
Port
Status
Indicator
ATTENTION: SecureConnect units are shipped inside the unit location
with stabs in the disconnected position. Prior to powering your horizontal
bus, you will need to place all SecureConnect units in the connected
position.