The cable used for the current should be installed at 600V AC minimum. The cable connector should be rated at 6
Amps or greater, and it should have a cross-sectional area of 16 AWG.

The current transformers should be mounted as close as possible to the meter. The following table gives the
maximum recommended distances for various CT sizes, assuming the connection is made via 16 AWG cable.

CT SIZE (VA)

MAXIMUM DISTANCE (CT TO EPM3000P)

2.5 VA

10 F

EET

5.0 VA

15 F

EET

7.5 VA

30 F

EET

10.0 VA

40 F

EET

15.0 VA

60 F

EET

30.0 VA

120 F

EET

WARNING:

DO NOT

LEAVE SECONDARY OF

CT

WHEN PRIMARY CURRENT IS FLOWING

. T

HIS MAY CAUSE HIGH VOLTAGE

,

WHICH OVERHEATS THE SECONDARY OF THE

CT. I

F THE

CT

IS NOT CONNECTED

,

PROVIDE A SHORTING BLOCK ON THE

SECONDARY OF THE

CT.


2.2 C

ONNECTING

V

OLTAGE

C

IRCUIT OF

P

OTENTIAL

T

RANSFORMER


For proper operation, the voltage connection must be maintained. If an error occurs, such as mistaking Line A for
Line B, a PH message appears, indicating a Phase Reversal (see Phase Imbalance and Reversal).

The cable required to terminate the voltage sense circuit should have an insulation rating greater than 600V AC and a
current rating greater than 0.1 A.

2.3 S

ELECTING THE

V

OLTAGE

F

USES

We recommend using fuses, although connection diagrams do not show them. Slow blow, 200 mA rating fuses
should be used.

The maximum voltage EPM3000P can handle 150V phase to neutral. If Suffix -G is added to the model number, the
maximum voltage to be used is 300V phase to neutral.

2.4 C

ONNECTION TO THE

M

AIN

P

OWER

S

UPPLY

The EPM3000P requires a separate power supply connection. Listed are the 5 different power supply options and
corresponding.

NOTE: F

OR

DC-

POWERED UNITS POLARITY MUST BE OBSERVED

. A

N EARTH TO GROUND CONNECTION TO CHASSIS IS

MANDATORY FOR NORMAL OPERATION

(

TERMINAL

3). D

O NOT GROUND THE UNIT THROUGH THE NEGATIVE OF THE

DC

SUPPLY

.

S

EPARATE GROUNDING IS REQUIRED

.

POWER SUPPLY OPTIONS

SUFFIXES

CURRENT

120V AC

N

O

S

UFFIX

.1

AAC

240V

AC A .05

AAC

24V DC

D

.5 ADC

48V DC

D1

.25 ADC

125V DC

D2

.1 ADC


3