INSTALLATION INSTRUCTIONS

Install the BT-1 in the most convenient location for ease of cleaning, maintenance and general operation. Avoid installing in
locations with drafts, close proximity to grease or vapor-producing appliances or other high ambient heat equipment. Allow
approximately 1” clearance on sides and back of unit for proper air circulation. Allow sufficient overhead clearance for
proper heat dissipation. This toaster must be level for proper operation and comes equipped with 1” adjustable legs for this
purpose. See instruction sheet enclosed for details.
Before operating this unit, be sure that the following two components are properly installed:
1.

The reflector tray is installed below the lower heating elements before shipping. It merely slides under the conveyor.
NOTE: Proper toasting cannot be performed without reflector tray installed.

2.

The toast receiving tray is packaged separately and must be installed before operating this unit. For front delivery
position,
slide the receiving tray into the toaster cavity below the control panel, making sure the lipped end is towards
the back. Place the lipped end over the 2 protruding pins located at the rear of the toaster cavity. For rear delivery
position,
slide the receiving tray into the cavity from the back of the toaster and place the lipped end over the 2 pro-
truding pins located closest to the front of the toaster. (See Figure 1)

WARNING

This toaster must be plugged

into the proper voltage which is

specified on the data plate

located on the back panel of

the toaster. Use of any other

voltage or altering of plug

will damage unit, void

warranty and may cause injury.

The circuit on which the receptacle is installed must be of adequate wiring size and sufficient capacity to meet the
requirements indicated on the unit data plate and in accordance with the National Electrical Code and local
electrical installation codes.