Operation 3

1. Engage the PTO

A. Engage the parking

brake.

B. Place the transmission in

the Neutral position.

C. Make certain the PTO

switch is in the ‘off’

position.

D. Start the vehicle engine.

E. Depress the clutch on manual

transmission vehicles.

F. Engage the PTO switch for cable and air type

shifters. Turn on the dash switch for electrical

operated style. Consult vehicle owner’s manual

for location and operation of OEM style in-dash

PTO switch.

G. Slowly release the clutch on a manual

transmission vehicle.

H. Allow a few moments to warm the hydraulic

system oil. In cold weather, it is especially

important to let the system run for a few minutes

before operating.

2. Turn on Power to Crane

Activate power to the crane and outriggers. The

power switch is located on the control panel in the

vehicle cab.

3. Position Outriggers

Once the PTO is engaged, extend the outriggers

using the control levers or switches marked

‘outrigger’. These may be located on the crane

base or in the compartment under the crane.

4.Operate Crane

A. Turn on necessary power to the crane.

B. Activate toggle switch for desired crane function.

See the Hetronic Remote Manual for detailed

information.

C. When operation is complete, store remote

handle in a safe, dry location.

5. Store Outriggers

Retract outriggers using the control levers or

switches marked ‘outrigger’.

6. Turn Off Power to Crane

Deactivate power to crane and outriggers.

7. Disengage the PTO

A. On manual transmission vehicles, depress the

clutch pedal completely.

B. Disengage the PTO switch.

C. If vehicle is a manual transmission, release the

clutch pedal gradually.

Chapter 2 - Operation

PTO Switch

Job-Site Set-Up

thoroughly plan the lift before positioning the vehicle.

consider the following:

1. The vehicle should be positioned in an area free

from overhead obstructions to eliminate the need

for repositioning.

2. Position the vehicle so that it is impossible for any

portion of the equipment to come within the

minimum required safe distance of any power line.

Maintain a clearance of at least 10 feet between

any part of the crane, load line, or load, and any

electrical line or apparatus carrying up to 50,000

volts. One foot additional clearance is required for

every additional 30,000 volts or less. Remember to

allow for winds that cause power lines to sway. It is

recommended that a signal person be used when

the vehicle is set-up near power lines.

3. The vehicle should also be positioned on a firm

and level surface that will provide adequate

support for the outrigger loading. Use extreme

caution when setting up near overhanging banks

or excavations.

4. The parking brake must be set on the vehicle and

the drive axle disengaged before performing a

crane operation.

5. The outriggers must be extended to stabilize the

truck before beginning operation.

Unit Operation Overview

1. Engage the PTO
2. Turn on Power to Crane

3. Position Outriggers

4. Operate Crane

5. Store Outriggers

6. Turn Off Power to Crane

7. Disengage the PTO

This chapter contains information regarding the

operation of Stellar manufactured articulating

cranes. Please study the following pages to ensure

your familiarity with the operation process. This

understanding is vital to the safe and efficient

operation of the crane.

NOTICE

The parking brake must be fully engaged

in order to operate any Stellar

Equipment.