Lochinvar RPV-I&S User Manual

Page 4

Advertising
background image

4

RPV-I&S

diameter PVC pipe. When venting with 4" (10.2 cm) PVC, use a 4" (10.2 cm) to

3" (7.6 cm) reducer to exit through the building wall with 3" (7.6 cm) PVC. Use

the 3" (7.6 cm) vent terminal supplied with the water heater to terminate on

the outside of the building. If the length of 3" (7.6 cm) PVC needed to go

through the wall is greater than 14" (35.5 cm), use 4" (10.2 cm) to go through

the wall and reduce to 3" (7.6 cm) PVC immediately after exiting the outside

wall. Refer to the venting illustrations on the following pages. Make sure the

vent pipe terminal elbow fitting is at least 1" (2.5 cm) away from the edge of

the wall.

NOTE: When using 4" (10.1 cm) PVC, use a 4" (10.1 cm) to 3" (7.6

cm) reducer and exit the building wall with 3" (7.6 cm) PVC using the

3" (7.6 cm) 90° vent terminal supplied. Two 45° elbows are equivalent

to one 90° elbow.

NOTE: ABS or CPVC pipes may be substituted for PVC pipe. Do not

mix ABS and PVC pipe in the same installation.

THROUGH THE WALL VENTING:

Cut a 3-1/2 inch (8.9 cm) diameter hole in the wall at the point where the vent
connector is going to pass through the wall. Use the proper cement to secure

the 90° vent terminal provided with the water heater to the vent connector.

The distance between the edge of the 90° vent terminal and the exterior wall
(see Figure 3) must be 1 inch (2.5 cm). Use the proper cement and assembly

procedures to secure the vent connector joints between the terminal and the

blower outlet. Provide support brackets for every 3 feet (.91 m) of horizontal
vent.

THROUGH THE ROOF VENTING: (VERTICAL VENTING)

Cut the necessary holes through the roof and ceiling and install the vent
connector as shown in

Figure 4. Make sure that the installation meets the local

codes and/or The National Fuel Gas Code ANSI Z223.1 (Latest Edition) or CGA/

CAN B149 Installation Code.

Figure 2

TABLE - 3

VENT CONNECTOR LENGTHS FOR 4" (10.1 cm) DIAMETER PVC

Terminating # of 90° Elbows Maximum Minimum

(excluding vent Length Length

terminal)
Through the Wall

1

70 ft (21.3 m)

2 ft (.6 m)

Through the Wall

2

65 ft (19.8 m)

3 ft (.9 m)

Through the Wall

3

60 ft (18.3 m)

5 ft (1.5 m)

Through the Wall

4

55 ft (16.8 m)

8 ft (2.4 m)

Through the Wal

5

50 ft (15.3 m)

12 ft (3.6 m)

Through the Roof

1

70 ft (21.3 m)

2 ft (.6 m)

Through the Roof

2

65 ft (19.8 m)

3 ft (.9 m)

Through the Roof

3

60 ft (18.3 m)

5 ft (1.5 m)

Through the Roof

4

55 ft (16.8 m)

8 ft (2.4 m)

Through the Roof

5

50 ft (15.3 m)

12 ft (3.6 m)

IMPORTANT

All of the Venting connections must be leak checked with a soap and

water solution upon initial start up of the water heater. Any leaks

must be repaired before continuing operation of the water heater.

Figure 3

Figure 4

TABLE - 2

VENT CONNECTOR LENGTHS FOR 3" (7.6 cm) DIAMETER PVC

Terminating # of 90° Elbows Maximum Minimum

(excluding vent Length Length

terminal)
Through the Wall

1

40 ft (12.2 m)

2 ft (.6 m)

Through the Wall

2

35 ft (10.7 m)

3 ft (.9 m)

Through the Wall

3

30 ft (9.1 m)

5 ft (1.5 m)

Through the Wall

4

25 ft (7.6 m)

8 ft (2.4 m)

Through the Roof

1

40 ft (12.2 m)

2 ft (.6 m)

Through the Roof

2

35 ft (10.7 m)

3 ft (.9 m)

Through the Roof

3

30 ft (9.1 m)

5 ft (1.5 m)

Through the Roof

4

25 ft (7.6 m)

8 ft (2.4 m)

Advertising