Installation

The basic installation procedure of parallel system is

the same as that of single module system. The fol-

lowing sections only introduce the installation proce-

dures specific to the parallel system.

Cabinet Installation

Parallel system composed of two UPS modules
The two UPS modules that will form the 1+1 system

should be placed side-by-side. Each battery cabinet

is placed next to its corresponding UPS module.

Preliminary Checks

Each UPS module should have the same rating, the

same firmware and the same hardware version.

Refer to the instructions in Conditions for Paral-

lel System on page 1.

Protective Devices

Refer to the instructions supplied in the Liebert NX

installation manual, SL-25215.

Power cables

Wiring of power cables is similar to that of single

module system (see the Liebert NX installation man-

ual, SL-25215). The bypass sources of all modules

should be the same, and the outputs should be con-

nected altogether correctly.

Parallel Control Cables

Make the connections described below on the paral-

lel logic board (M3) inside the Liebert NX:
• Connect one end of the DB-25 interconnecting

cable to the X2_1 connector of UPS 1 and the other

end to the X2_2 connector of UPS 2.

• Connect one end of the DB-25 interconnecting

cable the X2_2 connector of UPS 1 and the other

end to the X2_1 connector of UPS 2.

• Connect one end of the DB-9 interconnecting cable

the X1_1 connector of UPS 1 and the other end to

the X1_2 connector of UPS 2.

• Connect one end of the DB-9 interconnecting cable

the X1_2 connector of UPS 1 and the other end to

the X1_1 connector of UPS 2.

The connections are shown above in Figure 2.

Figure 2

Connecting 1+1 system parallel control
cables

Commissioning a Parallel System

Check the input and output wiring of each UPS mod-

ule. Ensure that the phase rotation sequence of the

main inputs and the bypass inputs and outputs of

each UPS module are the same. Ensure the parallel

cables are connected firmly.
It is assumed that the installation is complete, the

system has been commissioned by authorized per-

sonnel and the external power isolators are closed.

Before startup, disconnect the load.
Start the UPS modules separately and set the

parameters of each UPS module through configura-

tion software. Pay particular attention to the param-

eters directly relevant to the parallel system:
• UPS Configuration: Each UPS module belonging

to the parallel system should be set as Parallel

configuration.

• UPS ID No.: Each UPS module should have a

unique identification number in the parallel system.

• Parallel system requisite UPS units: Set the mini-

mum number of UPS modules to support the

user’s expected load. For 1+1 systems this settings

needs to be set to 1.

• Parallel system redundant UPS units: Set the

redundant number of UPS modules which will not

cause the parallel system transfer to bypass even

NOTE
The length and specifications of power

cables including the bypass input cables

and UPS output cables should be the same,

thus the load can be shared evenly in

bypass mode.

!

CAUTION

The operations in this section must be

performed by authorized electricians or

qualified technical personnel. If you have

any difficulties, contact Liebert Global

Services at 800-543-2378.

#1 UPS Module

#2 UPS Module

Parallel Board

Parallel Board

X5

X4

X2-2

X2-1

X2-2

X2-1

X4

X1-1

X1-1

X1-2

X1-2

1

2

4

3

Interconnecting Cables

1

2

Parallel Connection Board

UPS Unit

4

3

Advertising