NOTE:

1. Remove main burners from unit.

2. Check that burner venturi and ports are free of foreign

debris.

3. Clean burners with bristle brush and/or vacuum cleaner

- DO NOT distort burner ports or pilot location.

4. Reinstall burners in unit. Make sure front and rear of burners

are installed correctly in burner support brackets.

Also check for good flow of combustion and ventilating air to the

unit. Maintain a clear area around the heater at all times.

GAS VALVES

Figure 13 shows the type of combination manual gas control valve

and regulator used on these heaters.

If the gas valve becomes defective, repairs should not be

attempted. A new valve should be installed in place of the

defective one.

FIGURE 13

CHECKING THE INPUT

For appliance installation locations with elevations above

2000 feet, refer to HIGH ALTITUDE INSTALLATIONS section of

this manual for input reduction procedure.

1. Attach a pressure gauge or a manometer to the gauge port

and refer to the GAS PRESSURE REGULATOR section for

correct manifold pressure.

2. Use this formula to “clock” the meter. Be sure that other gas

consuming appliances are not operating during this interval.

3600 X H = Btuh

T

T = Time in seconds to burn one cubic foot of gas.

H = Btu’s per cubic foot of gas.

Btuh = Actual heater input.

Example:

T = 15.1 seconds

H = 1050 Btu

Btuh = ?
19 X 1050 = 199,999 Btuh

Should it be necessary to adjust the gas pressure to the burners

to obtain the full input rate, the steps below should be followed:

3. Remove the regulator adjustment sealing cap, see

Figure 13, and adjust the pressure by turning the adjusting

screw with a screwdriver.

Clockwise to increase gas pressure and input rate.

Counterclockwise to decrease gas pressure and input

rate.

4. “Clock” the meter as in step 2 above.
5. Repeat steps 3 and 4 until the specified input rate is achieved.
6. Turn the gas control knob to PILOT. Remove the pressure

gauge and replace the sealing cap and the allen wrench set

screw in the pressure tap opening.

WARNING

UNDER NO CIRCUMSTANCES SHOULD THE GAS INPUT

EXCEED THE INPUT SHOWN ON THE HEATER MODEL AND

RATING PLATE. OVERFIRING COULD RESULT IN DAMAGE

OR SOOTING OF THE HEATER.

When the heater is operating at full capacity, or full gas input, it

should consume 1 cu. ft. of gas in time indicated on Table 3.

TABLE 3

APPROXIMATE TIME REQUIRED TO CONSUME

1 CU. FT. OF GAS AT FULL CAPACITY

TIME REQ’D

INPUT

TYPE

BTUH

TO CONSUME

RATE

OF

PER

1 CU. FT.

(BTUH)

GAS

CU. FT.

OF GAS

154,000

NATURAL

1050

24.5 SEC.

199,000

NATURAL

1050

19.0 SEC.

Figures shown are valid for 0-2000 ft.(0-610m) installations. See

“HIGH ALTITUDE INSTALLATIONS” for deration requirements

over 2000 ft.(610m).

VENTING SYSTEM

Examine the venting system every six months for obstructions

and/or deterioration of the vent piping.

Remove all soot or other obstructions from chimney which will

retard free draft.

REMOTE STORAGE TANK

TEMPERATURE CONTROL

The water temperature in the storage tank (if used) is controlled

by the storage tank temperature control. The sensing element is

mounted in the hot water storage tank, see page 17.

A change in water temperature in the storage tank lower than

the tank temperature control setting will cause the sensor to

activate the circulating pump. The pump then circulates the water

through the heater where the thermostat senses the drop in water

temperature and activates main burner operation of the appliance.

If the storage tank temperature control is out of calibration, replace

with new control.

WARNING

SHOULD OVERHEATING OCCUR OR THE GAS SUPPLY FAIL

TO SHUT OFF, TURN OFF THE MANUAL GAS CONTROL

VALVE TO THE APPLIANCE.

Advertising
This manual is related to the following products: