WARNING: Test all gas piping
and connections for leaks after install-
ing or servicing. Correct all leaks at
once.

WARNING: Never use an
open flame to check for a leak.
Apply a mixture of liquid soap and
water to all joints. Bubbles forming
show a leak. Correct all leaks
immediately.

CAUTION: Make sure external
regulator has been installed between
natural gas supply and heater. See
guidelines under Connecting to Gas
Supply, page 7.

Figure 8 -Equipment Shutoff Valve

Pressure Testing Gas Supply
Piping System
Test Pressures In Excess Of 1/2
PSIG(3.5kPa)

1. Disconnect heater with its

appliance main gas valve (control
valve) and equipment shutoff valve
from gas supply piping system.
Pressures in excess of 1/2 psig
will damage heater regulator.

2. Cap off open end of gas pipe

where equipment shutoff valve
was connected.

3. Pressurize supply piping system

by either using compressed air or
opening propane/LP supply valve.

4. Check all joints of gas supply

piping system. Apply mixture of
liquid soap and water to gas
joints. Bubbles forming show a
leak.

5. Correct all leaks immediately.
6. Reconnect heater and equipment

shutoff valve to gas supply. Check
reconnected fittings for leaks.

Pressure Testing Heater Gas
Connections

1. Open equipment shutoff valve

(see Figure 8).

Figure 9 -Checking Gas Joints

INSTALLATION

Continued

CHECKING GAS CONNECTIONS

2. Open gas supply valve.
3. Make sure control knob of heater
is in the OFF position.
4. Check all joints from equipment
s h u t o ff v a l v e t o c o n t r o l v a l v e

(see Figure 9).
Apply mixture of liquid soap and
water to gas joints. Bubbles form-
ing show a leak.

5. Correct all leaks immediately.
6. Light heater (see Operating Heater,
page 9 ). Check all other internal
joints for leaks.
7. Turn off heater (see To Turn Off
Gas to Appliance, page 9 ).

Test Pressures Equal To or Less
Than 1/2 PSIG ( 3.5 kPa )

1. Close equipment shutoff valve

(see Figure 8).

2. Pressurize supply piping system

by either using compressed air or

opening gas supply tank valve.

3. Check all joints from gas meter to

equipment shutoff valve (see Fig-

ure 9). Apply mixture of liquid

soap and water to gas joints.

Bubbles forming show a leak.

4. Correct all leaks immediately.