Job aid: cable stripping requirements, Removing the power filler panel – Nortel Networks NN46200-310 User Manual

Page 30

Advertising
background image

30

DC power supply installation

1

Strip 0.81 in. (2.1 cm) of insulation from the ends of the cables.

2

Crimp the lugs onto the cables using a standard crimping tool.

CAUTION

Risk of injury by electric shock

Failure to properly crimp the lugs onto the cables
constitutes a safety hazard.

3

If necessary, use a heat gun to shrink the tubing around the
cable.

--End--

Job aid: Cable stripping requirements

The illustrations in this section provide details about cable stripping
requirements for the 8005DI DC and 8005DC power supplies.

Removing the power filler panel

A power filler panel maintains the proper cooling airflow in the Ethernet
Routing Switch 8300 chassis. You must remove the power filler panel from
the power bay when you install a power supply in a bay for the first time.

Nortel Ethernet Routing Switch 8300

Installation — DC Power Supply

NN46200-310

01.01

Standard

9 June 2008