10.1 Unpacking

Make sure that UPS unpacking is conducted on the paved floor indoor, which should be as close as

possible to the installing location. A building with overhead traveling cranes is expected to unpack large-

sized UPS. If a crane is not available, obtain a wide enough space for forklift operations. Also keep space

around the UPS to unpack the crate. Then extract the crate.

Points to be observed

(1) Retain all small articles during unpacking and installation.

(2) Make sure that exterior paint is not scratched and that the UPS cabinet is not damaged.

(3) Do not damage the UPS when using extracting tools.

(4) Do not remove the polyvinyl chloride cover, if provided, until installation.

(5) Packing materials should be disposed by the appropriate means after unpacking.

(6) In case of any abnormalities, immediately report this information to Toshiba or authorized

representatives.

10.2 UPS Clearance

When the UPS is installed, maintain the clearance around the UPS as shown in Figure 10.1.

Ensure that the front and top air vents are NOT blocked.

Figure 10.1 - UPS Clearance.

Top: 400mm (15” 3/4)

Front:

1,100mm

(43” 5/16)

Side: 0mm (0”)

Back: 0mm (0”)