Overview of Installation Steps

3–3

❐ DC fuses and fuse holders
❐ AC cable (2-conductor-plus-ground cable), sized appropriately for

load and application (if you are connecting to an existing AC circuit)

❐ 1/2 inch cable clamp (if connecting to an existing AC circuit)
❐ AC transfer switch (if connecting to an existing AC circuit that also

uses power from another AC source)

❐ Appropriately sized copper cable for the chassis ground
❐ Battery isolator (if connecting to a multiple-battery system)
❐ Battery selector switch*
❐ Alternator controller*
❐ High-output alternator*

* Consult

Appendix B

and

Appendix C

to determine whether you need

these components.

Overview of Installation Steps

Installing the PROwatt 1000 is straightforward. Here’s a summary of the
seven main steps:

1. Design the installation: calculate battery capacity and charging

requirements.

2. Choose a location.

3. Connect to an existing AC circuit (if required).

4. Install the remote On/Off switch.

5. Mount the inverter.

6. Connect the chassis ground.

7. Connect the DC cables.

PROWatt100.book Page 3 Friday, January 5, 2001 3:03 PM