Installing the trip paddle, Installing the trip unit mounting bracket, Trip paddle installed on the trip bar – GE Industrial Solutions ProTrip Conversion Kits DB-75, DBL-75, DB-100, DBL-100 User Manual

Page 7: Trip unit mounting bracket

Advertising
background image

SECTION 4. FRONT FRAME
BREAKER CONVERSION

Installing the Trip Paddle

1. Remove the

1

/

4

-20 bolt that fastens the draw-out

interlock lever to the common trip bar, as shown in
Figure 5.

2. Install the new trip paddle provided over the existing

interlock lever and secure it with the existing
hardware, as shown in Figure 5.

Installing the Trip Unit Mounting Bracket

The trip unit mounting bracket, shown in Figure 6,
mounts the flux shifter and trip unit to the breaker frame.

1. Mount the trip unit mounting bracket to the right side

of the breaker frame, as shown in Figure 8. Insert the

5

/

16

-18 x 1

1

/

4

" bolt with two flat washers up through

the frame and the hole in the bottom of the bracket.
Secure with a lock washer and nut.

2. Install the support bracket provided to strengthen the

top of the trip unit bracket, as shown in Figure 7.
Attach the support bracket to the trip unit mounting
bracket with the

1

/

4

-20 x

3

/

4

" bolt provided. Use the

bracket as a template to locate the position in the
breaker frame to drill a hole to accommodate a

1

/

4

"

bolt.

3. Slide the support bracket to the inside of the right

breaker frame member, as shown in Figure 8, and
secure it with the

1

/

4

-20 x

3

/

4

" bolt, lock washer, and

nut provided.

Figure 5. Trip paddle installed on the trip bar.

Figure 6. Trip unit mounting bracket.

Figure 7. Installing the support bracket..