SECTION 4 BACK FRAME

BREAKER CONVERSION
(CONTINUED)

Installing Phase Sensors (CT’s)
(High Range Instantaneous Kits Only)

Phase sensor installation for high range

instantaneous conversion kits is very similar to the
standard GE AK-25 or AKU-25 MicroVersaTrip

Plus and MicroVersaTrip

PM conversion kits. The

high range instantaneous conversion kits differ in

that the CT’s are supplied with an integral terminal

block and each phase sensor requires four (4)

separate electrical connections.

Phase sensor modification for the AK-25 circuit

breakers is completed by mounting the three (3)

current sensor assemblies to the back frame. See

Fig. 4-1, 4-2, and 4-3 on pages 13 and 14 of the

original installation instructions.

Step 1.

Insert the lower copper stud through the back

frame and attach it via the mounting screw.

Step 2.

Position the CT with its terminal toward the front

and top and loosely mount it to the stud with the
copper, 90

°

angled bus strap, and the bolt

provided. Be sure to install the anti-rotation plate

during this step and that the smaller diameter of

the copper stud is towards the top of the assembly

(Fig. 4-7). Note, Fig. 4-7 depicts a high range

instantaneous CT assembly on the top and an AK-

25 CT assembly on the bottom.

Step 3.

Align the assembly, then torque the two (2) 3/8”

bolts in the strap to 250 in.-lbs. each to assure

proper contact integrity.

Step 4.

Reassemble the front and back frames.

Step 5.

The wire harness can be connected only to the

CT’s after the front and back frames have been

joined. The pair of black wire leads in the wire

harness are connected to the terminals labeled “HI

INST” on each CT. Polarity for these black leads is

not critical.

CAUTION: The wire harness for high range
instantaneous conversion kits require four (4)

separate electrical connections for each phase

sensor in lieu of the two (2) connections in a

standard GE type AK-25 conversion kit. Be sure

to connect the wire harness to the phase sensors

as shown in Fig. 8-1 of this supplementary

publication.

WARNING: FAILURE TO PROPERLY CONNECT
THE WIRE HARNESS ASSEMBLY TO THE PHASE

SENSORS MAY RESULT IN INADEQUETE

PROTECTION FROM THE PROGRAMMER AND

DAMAGE TO THE CURRENT SENSORS.

Fig. 4-7. High Range Instantaneous CT Assembly

SECTION 7 TESTING AND

TROUBLESHOOTING