GE Industrial Solutions A Series Lighting Control Panelboards Replacement of Controller User Manual

A series, Lighting control panel boards

Advertising
background image

g

A Series

®

Lighting Control Panel boards

DEH41095 Installation Instructions R02

WARNING: Danger of electrical shock or injury. Turn OFF power service to the line side of the panel
board or switchboard before working inside the equipment or removing any component. Equipment
is to be installed and maintained by properly trained and qualified personnel only.
















































Replacement of Controller

Transformer
Secondary wires

Power in
terminal at
Controller

FIG 1

Catalog No.

Qty.

Description

ASRGLCTDP

1

Controller with out Ethernet

ASRGLCTDPE

1

Controller with Ethernet


Removal of Controller:

1. Ensure that the Installer is properly grounded while handling

Controller

2. Remove the front cover & dead front of the Panel board/

Integrated Switchboard.

3. Lift up to unplug the Power in terminal at controller see fig 1. Also

disconnect all the communication ports such as ethernet etc to
the controller.

4. Unscrew the DB25 connector screws & remove the DB25

connector cable ends at the controller box sides (both sides).

5. Unscrew the controller cover mtg screws (qty-2) and lift the

controller cover upwards.

6. Unscrew the hold down bracket screws and remove the hold

down brackets from both sides of controller box.

7. Remove the Caplugs on the controller box (qty-4)
8. Unscrew the Controller board supports mtg screws (qty-2)
9. Unscrew the Ground stud screws (qty-3 )
10. Pull back and lift the controller assembly along with the controller

board supports.

11.

Pull off the controller board supports (qty-2) side ways and save
for new controller.

Reinstallation Instructions:

1. Push on the saved controller board supports (qty-2) onto each

end of new controller.

2. Drop this assembly along with the controller board supports at an

inclination and push forward in the controller box so as to have
proper seating (ensure that the hooks provided on the controller
board supports locks in the controller box).

3. Tighten the ground stud screws (qty-3) so as to hold the controller

board firmly to the controller box. Torque to 10 lb-inch.

4. Tighten the controller board support mtg screws (qty-2) to torque

of 15-20 lb inch

5. Push In all the Caplugs in to the controller box.
6. Drop down the controller cover in to the mtg holes provided in the

box and other end of the controller cover to seat in the controller
board support recess grooves.

7. Tighten the controller cover mtg screws to torque of 15-20 lb-inch.
8. Assemble the hold down bracket both sides and tighten it to the

box with the hold down bracket screws to torque of 15-20 lb-inch.

9. Push the ends of the DB25 connector cable ends to the controller

connector both sides and tighten the knurled screws at end of
each cable connector to torque of 5 Lb-inch.

10. Plug in the transformer secondary wire connector to Power in

terminal on controller.

11. Connect all the communication port wires such as ethernet etc to

the controller.

12. Install dead front and front cover of the panel board / Integrated

switchboard.

Recessed
groove

DB25 Connector
Cable

Controller
Box

Controller
Board support
mtg screws

Caplugs

Hold Down
Bracket

Hold Down
bracket mtg screw

Controller
ASRGLCTDP
ASRGLCTDPE

Ground stud
screws

Controller Board
Support

Controller
Cover

Controller cover
mtg screws

GE Consumer & Industrial General Electric Company, Plainville, CT 06062

2004 General Electric Company

DEH41095 R02