DEH41036 Installation Instructions

R01

g

Commercial Metering Switchboards

Splicing and joining sections

Application

These instructions are provided for the installation of

splice bars, and to join switchboard sections at the

installation site for ease of installation. These steps must

be performed prior to setting the switchboard sections on

the final pad and termination of cables.

1. Check installed hardware. Make sure hardware is

installed at the end of the bus bar on each section as

shown in the picture in below:
























Installation

WARNING: Danger of electrical shock or injury.

Turn

OFF

power ahead of the switchboard

before working inside the equipment or

removing any component

.

Equipment is to be

installed and maintained by properly trained

and qualified personnel only.

eep in mind this hardware is loose and is held to

2. Check splice dimensions. Compare the dimensions of

the picture above the first section is 5” deeper then

K

the bus by a rubber band. To avoid losing any

hardware, do not remove the rubber band until the

splice bars are going to be installed. The splice bars

are located in the Section marked with the yellow

label “ Splices in this section.”

the bus against the splice bars to ensure the 2 sections

are going to be joined successfully. First, measure

from the front of each section to the horizontal bus,

then subtract the distance of the first sections from

the second. This should be equal to the length of the

splice bars.














In

the second one, and the main bus is located an equal

distance from the rear. Therefore flat bus splices are

required.