GE Industrial Solutions Spectra Series Power Panelboards APM2404PQM, APM2403PQM, and APM2084PQM User Manual

Page 2

Advertising
background image

Figure 3. Terminal board in the meter module.

4. Run wires down the side of the interior.

Determine

the shortest route to the equipment neutral (if
applicable) and ground using the side rails of the
panels. Be sure that the breaker cables will not
interfere with the wires. Attach saddles [4], spaced
approximately 1 foot apart, with tie wraps [3]. Wipe
off the metal with a paper towel or equivalent at the
point of saddle attachment. Use tie wraps [3] to secure
the wires to the saddles.

5. Attach the wire to neutral and ground

. Cut and strip

the free end of the ground wire and attach to the
equipment ground, as shown in Figure 4. Select the
lug hole closest to the metering module. Do the same
for the neutral (if applicable), as shown in Figure 5.
Tighten the screws to the torque levels specified on
the component labels.

Figure 4. Attach the 12-gauge wire to the equipment ground.

Figure 5. Attach the 14-gauge wire to the equipment neutral.

g

GE Industrial Systems

General Electric Company
41 Woodford Ave., Plainville, CT 06062

DEH40394 R02 0901

© 2001 General Electric Company

These instructions do not cover all details or variations in equipment nor do they provide for every possible contingency that
may be met in connection with installation, operation, or maintenance. Should further information be desired or should
particular problems arise that are not covered sufficiently for the purchaser’s purposes, the matter should be referred to the
GE Company.

Terminal

VN

Terminal

GND 6

14-Gauge

Wire

12-Gauge

Wire

Slotted
Screws

Equipment

Ground

Ground

Wire

Equipment

Neutral

Neutral

Wire

Advertising