Section 4. Installation


The test cabinet should be installed on the wall at a
location where maintenance and testing of the breaker
can be conveniently done.
Make sure that the green ground conductor is connected
to electrical ground.


Conduits may be installed for cables to supply control
power for testing. Two 1-inch diameter grommets are
located on top accomodate wiring. Refer to the wiring
diagrams figures 2, 3, and 4 for control power
connections.

Section 5. Maintenance


The contact surfaces of the coupler require periodic
lubrication to inhibit oxidation and minimize friction. It
is recommended that during each maintenance interval,
the pins of the breaker coupler be lightly coated with
0282A2048P009 grease.

Aside from keeping the unit clean and dry, the most
important thing is to return the clamp to the cabinet area
when not connected to a breaker.



Fig. 2. Test Cabinet Outline Drawing