To load the downhole tool in the unit, slide the vise left or right as needed. Adjust the vee-
saddle to support the tool when set into the vise. Set the tool into the vise. Position the tong
for make up or break out as needed and set the tong onto the tool. Adjust the vise and tong
as described and latch the vise chain and tong chain.

CAUTION: The vee-saddles must be used to support the tool while torquing.

Vise and Tong Adjustment

Release the cam lock on the tong and vise by depressing the cam lever and moving the pawl to the unlocked
position (see figure 3 on page 18). Slide the chain through the tong or vise as needed to latch the chain screw
nut into the jaw. Move the pawl lever to the locked position and release the cam lever. Check that the cam
lever is latched. Tighten the chain screw nut on the vise until hand tight. Tighten the chain screw nut on the
tong until it is hand tight and then loosen the chain screw nut on the tong 1/2 turn to provide proper
ratcheting.