3.3 Installation Procedure

1.

Install the CE-G enclosure so that the gas utility box of the CE-X

enclosure fits into the gas utility box cutout on the CE-G (dashed line) as

pictured below. Ensure the two cabinets are placed flush against each

other.

2.

With the two cabinets sitting flush against each other, mark the anchor

bolt pattern onto the concrete pad using the four slotted anchor bolt

holes found in the corners of the base plate of the CE-G enclosure as an

template.

3.

Also, mark the hole which will be used to bolt the cabinets together

(located at the lower left corner of the gas utility box cutout).

1

3

Fig. 3.1, Gas utility box cutout, connection bolt location