Installation Instructions

-- RESILIENT TILE FLOORING

Rubber Tile and Stair Tread Installation Instructions

Installation of Endura Rubber Floor Tile By Burke Flooring

Only Approved Adhesives Must Be Used For Warranty to Apply:
BR 721™ Epoxy Adhesive – Solvent Free
BR 725™ Urethane Adhesive – Solvent Free

BR 711™ – Solvent Free – For Treads Only – Not for Tile

6” StepBond™ Tread and Landing Tape


I. Storage
A. Check tiles for completeness of order. Check for correct color and profile.
B. Store tiles off the ground and out of the elements. Do not stack skids, or stack
other materials on tiles or treads.
C. If the tiles are to be re-stacked, the tiles must be stacked profile to profile and
back to back to avoid mold release or wax transfer from the profile side to the back
side.
D. Prior to installation, the tiles and adhesive must be conditioned to an ambient
temperature at the actual job site of not less than 59°F (14°C) to not more than
85ºF (29ºC) for at least 48 hours. In severe climates an 8 day conditioning period
may be necessary.


II. Sub-floor Preparation - For Additional Required Information, refer to ASTM F-
710 - Practice for Preparing Concrete and Other Monolithic Floors to Receive
Resilient Flooring.


A. Concrete Sub-floor

1. On-grade and below-grade sub-floors must be protected against ground

moisture with a properly installed membrane type moisture barrier.

2. New concrete sub-floors should be allowed to cure a minimum of 30 days.
1. Sufficient moisture test sampling should be made. The emission of moist

vapor from the slab should not exceed 5 lbs. per 1,000 sq. ft. per 24 hours.