AAON M2-036 User Manual

Page 69

Advertising
background image

69

7. Check all high and low voltage

wiring connections for correctness
and tightness.

8. Check unit for correct incoming

voltage per the data plate.

9. Check the security of the locking

system on all blower bearings

10. Turn the unit power on.
11. Turn the unit blower on and check

for correct rotation.

12. If correct, take blower amp readings

and compare to see if the amp draw
is within the safety factor area of the
motor. Once correct, turn blower
off.

13. Turn on the first stage of heating

− Check amp draw of each

element of each stage

− Ensure blower started w/

electric heat

− Check for temperature rise

across heating section while
all stages are on

− If temperature rise is within

range, turn all heating calls
off

− Check to see that blower

stops


Refrigerant (DX) Cooling Section
Procedures:


1. Perform final visual inspection.

Check all equipment, ductwork, and
piping to verify that all work is
complete, and equipment is properly
installed and mounted. Improperly
installed equipment, or ductwork can
affect readings.

2. Perform condenser start-up checks in

addition to these air handler checks
according to the condenser
manufacturer’s instructions.

3. Ensure there is no construction

debris in the unit.

4. Check the unit for external damage.

5. Note all accessories installed.
6. Ensure that drain P-trap is properly

installed.

7. Check all terminal blocks, fuses, fuse

blocks, and contactors for
correctness.

8. Check all high and low voltage

wiring connections for tightness.
Check unit for correct incoming
voltage per the data plate.

9. Check the security of the locking

system on all blower bearings

10. Turn the unit power on.
11. Turn the unit blower on and check

for correct rotation.

12. If correct, take blower amp readings

and compare to see if the amp draw
is within the safety factor area of the
motor.

13. Check and record ambient

temperature.

14. Check for Guaranteed Off Timers

(GOT) and Time Delay Relays
(TDR).

15. Start the first stage cooling circuit

and blower circuit.

16. After all stages of cooling have been

on for at least five minutes, record
the return air temperature and supply
air temperature.

17. Check the temperature difference

across the evaporator coil.


Commissioning
The commissioning of an air conditioning
system is the process of achieving,
verifying, and documenting the performance
of that system to meet the operational needs
of the building. This may not be a formal
process in smaller structures, but some form
of owner acceptance will occur.

Adjustments made during the
commissioning phase may include air or
water balancing, or configuration of controls
and operational sequences.

Advertising
This manual is related to the following products: