HOMA Single Phase Pump Start Up Procedure User Manual

Single phase pump start-up procedure

Advertising
background image

Publication

88PN3015A

Please Contact Technical Support At 203-736-8890 With Any Additional Questions

Please Be Prepared To Provide Pump Serial Number During Call

Page

1 of 1

Single Phase Pump Start-Up

Procedure

Run Capacitor sizing can vary depending on the incoming supply voltage provided. HOMA
Single Phase pumps are provided with a Start and a Run Capacitor sized for 220-230V
under load. Frequently, the available line voltage is considerable different than indicated,
and the start or run capacitors may need to be resized to match the available field voltage.
The following procedure will allow you to verify proper operation of your single phase pump,
and/or make necessary changes to your capacitors to correct for your power supply.

After verifying wiring is in accordance with your pump requirements, start pump and record
the following readings from each of the (3) pump cable leads.

Current under load:
U1 _________Amps,> U2 __________Amps,> Z2 __________Amps

Should be (highest reading) (middle reading) (lowest reading)


Lead U1 (common) should have the highest current reading. Lead Z2 (start) should have
the lowest reading.

If Z2 current draw is greater than the current draw of either U1 or U2, a smaller size Run
capacitor (lower microfarad rating) is required to correct the condition. Example: If a 60 uf
Run capacitor was supplied, change to a 50 uf Run capacitor and check current readings.
Typically, only one step down in capacitor size is required, but in certain instances 2 steps
may be required.

( ) The standard capacitor kit provided includes: _______uf start capacitor

_______uf run capacitor.

( ) Additional run capacitors have been included for use in tuning the pump to match
available line voltages for optimum performance.

______uf


______uf


______uf

Advertising