5. Open the outlet (downstream) block valve.

6. Slowly open the inlet (upstream) block valve to

about 25% open, observing the inlet (upstream)
pres sure gauge. The reg u la tor should be fl ow-
ing. Adjust the loading system pressure control
device setpoint pressure upwards until the main
valve fl ow is shutoff. Observe the inlet pressure
gauge to ensure not over pressurizing.

7. Continue to open inlet block valve until at least

50% open. Set loading system pressure control
device upwards to approximate 80% desired main
valve pressure level.

8. Fully open inlet block valve.

9. Begin to slowly close the bypass valve if installed.

10. Develop

system

fl ow to a level near its expected

normal rate, and reset the regulator set point by
adjusting the loading system pressure control set
point to the desired level.

11. Reduce system fl ow to a minimum level and

observe pressure set point. Inlet pressure will
decrease from the set point of Step 10. The
max i mum build in inlet pressure on increasing
fl ow should not exceed 10%. If it does, consult
factory.

VI. SHUTDOWN

1. Shutoff auxiliary loading pressure source.

2. Shutoff inlet block valve.

3. Shutoff the outlet block valve.

VII. MAINTENANCE

A. General:

1. The regulator may be serviced without re-

mov ing the regulator from pipeline. The

reg u la tor is designed with quick-change trim

to simplify maintenance.

2. Record the nameplate information to req ui -

si tion spare parts for the regulator. The
in for ma tion should include: size, KM Product
Code, and Serial Number.

3. Refer to Section VIII for rec om mend ed spare

parts. Only use original equip ment parts sup-

plied by Cashco/KM for re build ing or re pair ing

regulators.

4. Owner should refer to owner's pro ce dures for

removal, handling, cleaning and disposal of
nonreusable parts, i.e. gaskets, etc.

NOTE: On regulators originally sup plied as
“oxygen clean” – Opt-55, main te nance must
include a level of clean li ness equal to Cashco
cleaning stan dard #S-1134.

5. The Inner Trim Assembly (ITA) is re moved and

re placed in the body (23) as an as sem blage of
parts. The ITA con sists of the fol low ing parts:

Item

Dynamic

Side

No.

Seal Type

Part Description

7 ...................... All ........................Diaphragm Cap Screw

7 ...................... All ........................... Diaphragm Lock Nut

8 ...................... All .......Upper Diaphragm Pressure Plate

9

...................... All

...................................... Diaphragm(s)

10 ..................... All ..........Lower Diaphragm Pusher Plate

13

..................... All

....................... Piston/Guide

Bearing√

14

..................... All

......................................... Stem

Seals

14.1 ............... All ................................ Upper Stem Seal

14.2 ............... All ................................Middle Stem Seal

14.3 ............... All ..............................Lower Stem Seal√

14.4 ............... All ................ Lower Pusher Plate Gasket

20

..................... All

...........................................Valve

Plug

27 ..................... All ........................... Dynamic Side Seal *

27.1

...............CP

..................................... TFE Cap Seal

27.2

...............CP

......................... O-ring Energizer/Seal

27.3 .............. UC .......... U-Cup Seal w/Metal Energizer

27.5

...............PR

................................. Piston Ring Seal

27.6

...............PR

................. Piston Ring SST Energizer

28

..................... All

............................................ Seat

Disc

29 ..................... All ............................... Seat Disc Washer

30 ..................... All ......................................Seat Disc Nut

* Possible option is with NO dynamic side seal.

√ 2-1/2" thru 4" body sizes only.

SECTION VII

4. Relieve the trapped upstream and downstream

pressure and loading pressure.

5. The regulator may now be removed from the

pipe line or disassembled for inspection and pre-
ven ta tive main te nance while in-line.

A detailed view of the dynamic side seal parts
is shown in Figure 1 on the next page.