Dual Gate Installations

Two operators can be used in dual gate installations. The operators
communicate with each other through the 3-wire COMM LINK terminals.

When one operator activates, the COMM LINK connection signals
the other operator to activate. Each operator functions independently,
controlling its gate and monitoring its inputs and accessories.

A three-wire shielded conductor cable is required to connect two
operators together for dual operation. Use Belden 8760 Twisted Pair
Shielded Cable (or equivalent) only – P/N 2500-1982, per foot).

NOTE: The shield wire should be connected COMM LINK terminal

“C” in both operators.

Three of the programming functions available are only used for dual gate
installations:

• Dual Gate Enable

Dual Gate Enable must be set for all dual gate installations.

• Stagger Mode

The Stagger Mode function determines if the operator has a delayed
open or a delayed close. In dual swing gate installations, typically one
operator is programmed for delayed open, and the other operator is
programmed for delayed close.

• Stagger Delay Time

The Stagger Time sets the length of the delay for the Stagger Mode.

See Pages 11 & 13 for details on these three dual gate programming
functions.

Set the following parameters in each gate operator individually in a single
gate mode before connecting the network cable and operating in dual
gate mode.

4. 1. Open and Close Limit settings

5. 2. Open and Closed direction inherent

entrapment protection (OC & CC)

After these parameters have been set, and each operator has been
tested independently and is functioning correctly in single gate mode,
then set BOTH operators to dual gate (dg) in the Paired Mode setup step
under Basic Programming steps.

Optional In-Cabinet Heater

The operator can be ordered with an optional cold weather
package that includes an in-cabinet heater to keep the drive
train and electronics warm in cold environments.

In-cabinet heaters can also be ordered separately and
should be wired to the operator as shown in Figure 14.
Contact Technical Services for heater wiring information for
a specifi c voltage and phase of operator.

OPERATOR #1

OPERATOR #2

USE BELDEN 8760 TWISTED PAIR

SHIELDED CABLE OR EQUIVALENT

SHIELD

CONNECT SHIELD

WIRE AT BOTH ENDS

DUAL GATE
COMM LINK

WIRING

CONNECT

C - C

B - B
A - A

SHIELD

Figure 13. COMM LINK Wiring

115 VOLT HEATER (P/N 2510-262)

208/230 VOLT HEATER (P/N 2510-273)

WHITE

BLACK

SINGLE PHASE 115V, 208V, & 230V MODELS

(All heaters have built-in switch and thermostat)

POWER BOX

THREE PHASE 208V & 230V MODELS

208/230 VOLT HEATER (P/N 2510-273)

CONTACTOR

THREE PHASE 460V MODELS

460 VOLT HEATER (P/N 2510-354)

CONTACTOR

CONNECT TO LEADS LABELED

"ACCESSORY POWER CONNECTION"

Figure 14. In-cabinet Heater Wiring