PRE-START CHECKLIST FOR PATRIOT

Internal Mix System


ACTIVITIES MUST BE DONE IN THE SEQUENCE SHOWN, AND MUST BE TICKED OFF

AS COMPLETED. USE THIS CHECKLIST IN CONJUNCTION WITH THE OPERATING

MANUAL FOR THE PATRIOT UNIT.


ACTIVITY

NO.

ACTIVITY

TICK WHEN
COMPLETED

Priority

Put on Respirator as specified for spray painting,
Protective Clothing, Eye Protection, and PVC Gloves

1

Tools and materials are available for pre-start checks.

2

Incoming airline is ½ inch.

3

Incoming airline is connected to the inlet manifold.

4

Ground straps are connected to the resin drum and to earth.

5

Incoming air valve is in the OPEN position.

6

Air supply is ON.

7

Seat catalyst and resin seals on Pro Gun. (if applicable)

8

Remove nozzle cap, nozzle and mixer.

9

Check for oil in the pump reservoir, fill 1/3 full.

10

Check that there is Catalyst in the Catalyst Bottle.

11

Check that the Catalyst Bottle Cap and Screen are in place.

12

Place the Resin Pick-up wand in the resin supply container.

13

Place the end of the Resin Return Hose in the resin container.

14

Fill the Solvent Flush Tank.

15

At the Manifold, turn the Air Pressure on to the Solvent Flush
Tank (50

– 60 psi)

16

Flush the mix chamber on the Pro Gun.

17

Remove air from the Catalyst feed line to the Catalyst Pump.

18

Close the ball valve below the Surge Chamber.


THE UNIT IS NOW READY TO BE STARTED UP. GO TO

– “FIRST TIME START UP – Internal Mix”


ABNORMAL CONDITIONS OBSERVED AND CORRECTED

Abnormal Condition

when
corrected



OPERATORS NAME _______________________________________DATE: _____________


SIGN OFF WHEN PRE-START CHECKS ARE COMPLETED: ____________________________