11

SECURING THE 2nd BEAM WITH
DROP-IN RIDGE/EAVE BARS

INSTALLING PURLINS AND RIDGE BARS

COMPLETING THE 1ST BAY

IN 20’ MID BAYS ONLY, INSTALL A SUPPORT PURLIN
BETWEEN THE EAVE AND THE PURLIN AT THE MID-RAFTER
LOCATION. THIS SUPPORT WILL BRACE AGAINST INWARD
DEFLECTION OF THE EAVE BAY THAT COULD OTHERWISE
RESULT IN WATER PONDING IN THE 20 FT BAY.

USE LIFTING CRADLES TO
POSITION 2nd END.

DROP-IN RIDGE/EAVE BARS
CONNECT 1st AND 2nd BEAMS.

DROP ONE HOOK END OF

BAR INTO EAVE FITTING.

USE SAME TECHNIQUE AS ABOVE AND
THE LONG LIFTING POLE WITH CRADLE
TO INSTALL THE PURLINS AND RIDGE
EAVE BAR (AT THE PEAK)

REMOVE CROSS-CABLE FROM 2ND BEAM