INSTALLATION

3.9

Injection Check Valve and Discharge Tubing Installation

The Injection Check Valve prevents backflow from a treated line. Install the injection
check valve at the location where chemical is being injected into the system. Any size
NPTF fitting or pipe tee with a reducing bushing to 1/2" NPTF will accept the injection
check valve. Teflon

®

tape should only be used on threads that are connected with pipes.

When installing the Injection Check Valve, be sure to position it so that the valve enters
the bottom of your pipe in a vertical position. Variations left and right within 80° are
acceptable (see illustration).

After cutting an appropriate length of tubing, connect tubing to the injection check valve
then back to the discharge side of the pump head. Make sure it does not crimp or come
into contact with hot or sharp surfaces (see Tubing Connections, Section 3.3).

Typical Injection Check Valve Installations

1" Pipe Tee

Do NOT use

Teflon tape

On machined

Threads

40°

Variation

Acceptable

Injection

Check Valve

Pipe Cross

Section

CORRECT

Use Teflon

Tape here on

Pipe threads only

Injection

Check Valve

Reducing

Bushing

1" to 1/2" NPT

(Customer Supplied)

Flow

Flow

40°

Variation

Acceptable