1.

Dig five (5) holes @ 42" deep and 24" diam as shown on the plan view.

2.

Place the three 2-7/8" od back posts (A) in the three back holes.

3.

Place the two 2-7/8" od end posts (B) in the end holes with lugs parallel to the front opening.

4.

Each post shall be 12'-0" above ground and 10'-0" on center. Place a horizontal brace (C)
on the ground between each of the posts. Place a rail end fitting (P) on each end of these
braces. Place a brace band (Q) over each post adjacent to each rail end fitting. Bolt rail
end fitting to the corresponding brace band. Make sure the horizontal brace fits in to the rail
end fittings at least 1". If they don't, adjust the posts accordingly.
**NOTE: All carriage bolt heads are facing the playing field.

5.

With the proper spacing assured, plumb all posts and pour the concrete footings. Allow
24 hrs. for concrete to set and then proceed as follows.

6.

Attach three angle fittings (G) to back posts (A).

7.

Hood Post Erection: Insert the three hood support posts (D) into open end of the three angle
fitting (G) on back posts, with bent portion toward the playing field.

8.

Tighten set screws holding hood posts in place.

9.

Install mid (C) and front (E) horizontal tie members, using three "T" fitting (H). Attach
triangle supports (F).

10.

Install horizontal braces (C) between the posts above ground. These braces can be
installed in a manner similar to directions in item 4. Larger size bands (M) and (R) are
furnished for use on the angle fittings.

11.

Unroll the 9 ga wire (I) from end of roll. Stretch the wire for measuring and open the
knuckle on each side of the roll at 9'-7" and weave out one strand of wire.

12.

Weave a tension bar (L) through the last loops on the unknuckled sides. Place this wire
against playing field side of one of the wing panels with the tension bars parallel to the
uprights.

13.

Stretch wire on the wing panels. Slip 6 tension bands (N) over each post adjacent to the
tension bars. The tension bars must be offset so that the wire will be stretched on the
playing field side (inside) of the backstop. Equally space the 6 tesnsion band up and down
the posts on each side of the wire panel and bolt into position.


**NOTE: If the wire is too loose, remove a strand of wire as in item 11 above or,

if the wire is too tight to fasten into position, reweave into panel, the strand of
wire removed in item 11 above.

14.

Stretch Wire Back Panel The back two panels will be stretched in one piece between
outside back posts (A). The length of the wire needed should be 3" shorter than the
distance between the inside of the two corner posts (A). (Make sure wire is stretched when
measuring)

15.

Place this wire against the playing field side of the backstop with the tension bars (L)
parallel and adjacent to posts (A). Stretch and secure into position with 6 tension bands (N)
on each post.

16.

Install and stretch wire in the opposite wing as described in items 12 and 13 above.

17.

Stretch Wire - Hood Panels

Install wire on hood, one panel at a time. Measure out the

11 ga chain link (J) wire as in item 12 above. and install as in item 13.

**NOTE: Wire goes on the outside (top) of hood.
18.

Stretch Wire - Corner Panels Install wire on corner panels using 11 ga chain link (K) wire.
Cut off extra wire where necesssary. Tie at 12" along top side panels.

19.

Use tie wire (O) and tie all chain link to the adjacent horizontal braces at approx. 18" apart.

20.

Tighten all set screws and bolts & nuts.