System Sensor WFD Explosion Proof User Manual

Page 2

Advertising
background image

4. Seat the O-ring or gasket against the saddle and mount the detector di-

rectly to the pipe. Carefully roll the vane opposite the direction of flow
and insert it through the hole. Seat the saddle firmly against the pipe so
that the locating boss goes into the hole.

5. Install the U-bolt, tightening the nuts alternately to ensure a uniform

seal. See Table 1 for torque values.

6. Remove the metal cover with the tamper-proof wrench provided. Manu-

ally actuate the limit to check for binding. If the vane binds, remove the
detector and correct the cause before proceeding.

CAUTION

Be sure the direction-of-flow arrow points in the right direction or else water
flow will go unreported. See Figure 3.

fiGUre 1. moUnTinG dimensions:

6.75˝

4.019˝

5.019˝

PLASTIC

VANE

PIPE

DIAMETER

PLUS 6.5˝

PIPE

U-BOLT

NUT

PIPE

SADDLE

U-BOLT

W0238-00

fiGUre 2. moUnTinG hoLe LocaTion:

WRONG

RIGHT

REMOVE BURRS FROM EDGE OF HOLE. CLEAN OUT SCALE

AND FOREIGN MATTER FROM INSIDE WALL OF PIPE.

W0106-00

TabLe 1:

Wfd Model

Hole Size (in)

ToRque

20, 25, 35

1

1

/

4

30–35 ft.-lb.

30-2, 40, 50, 60, 80

2

55–60 ft.-lb.

D770-24-00

2

I56-1452-005R

PreoPeraTion TesTinG
1. Fill the sprinkler system and check for leaks around the waterflow detec-

tor. If it leaks, first check for the proper torque on the U-bolt nuts. If the
leak persists, drain the system and remove the detector (refer to Mainte-
nance). Check for dirt or foreign objects under the gasket, and make sure
that the pipe surface is not dented. Reinstall the detector and check again
for leaks. Do not proceed until all leaks have been stopped.

2. Connect an ohmmeter or continuity tester across the COM and B-NO

switch terminals. The ohmmeter should indicate an open circuit.

3. Deflect the actuator lever and hold it until the pneumatic delay shaft

releases the switch buttons. The ohmmeter or continuity tester should
show a short circuit after the delay has elapsed. If there is no delay,
check the setting of the delay adjustment dial.

fiGUre 3. assembLY diaGram:

COVER

TERMINAL BLOCK

(REPLACEMENT P/N A77-01-02)

GROUND

SCREW

(GREEN)

CONDUIT

ENTERANCE

U-BOLT NUT

DIRECTION OF

FLOW ARROW

PIPE

U-BOLT

DELAY

MECHANISM

(REPLACEMENT P/N

A3008-00)

PIPE SADDLE

PLASTIC VANE

ROLL PADDLE (VANE)

OPPOSITE OF FLOW

ARROW WHILE INSERTING

SADDLE

GASKET

HOLE SIZE

(REFER TO TABLE 1)

W0183-00

WirinG
1. All models have two SPDT switches. Switch contacts COM and B-NO

are closed when water is flowing and open when it is not. Connect the
switches, as shown in Figure 4, depending on the application.

2. When connected to a listed sprinkler/fire alarm control panel, the initiat-

ing circuit must be non-silenceable.

3. A ground screw is provided with all waterflow detectors. When ground-

ing is required, clamp wire with screw in hole located between conduit
entrance holes. See Figure 3.

4. If a second conduit entry is required, remove the plug using a hex wrench.

WARninG

High Voltage. Electrocution Hazard. Do not handle live AC wiring or work on a
device to which AC power is applied. Doing so may result in injury or death.

When utilizing switches at voltages greater than 74VDC

or 49VAC

means to provide all–pole disconnection must be incorporated in the fixed
wiring, such as a circuit breaker.

Advertising