3. Installation

3.1. LIFTING AND UNLOADING

The machine can be transported by two means:
- with a forklift truck. To do so, the machine is secured on a
pallet with four hex bolts.
- by several persons slide the machine from the pallet.
CAUTION
Do not carry the machine holding it at the infeed and outfeed
tables, these are not designed to withstand the tensile load by
the machine weight.

3.2 POSITION OF THE MACHINE

CAUTION
It is prohibited to install the machine in explosive environments.
Ensure that the floor area around the machine is level, well
maintained and free from loose material such as saw dust or
other wood waste.

1. Remove four mounting bolts from the machine base.
2. Lift machine off the pallet and set down on the floor.
3. Fix the machine to the floor. Fix the machine feet and fix on
ground by means of expansion bolts (not supplied).

3.3 IDENTIFYING SHIPPING BOXES

BEFORE ASSEMBLY
It is advisable that before unpacking to have plenty of paper
towels or cloths available to clean off the rust preservative.

FIG. 1

FIG. 2

3.4. INSTALLATIONS OF LOOSE PARTS

The machine is supplied almost assembled. Prior to use, the
handwheel must be fitted.

Install the handwheel (A, Fig.4) with set screw (B, Fig.4)

FIG. 4

B

A