1. Bring the complete Solar Controller Kit, including the Remote and Controller Box, to the attic.
2. Check and make sure the Thermo Switch on the back of the Remote is set to the OFF

position

3. Install the Controller Box on a nearby rafter close to the underside of the roof with the

provided mounting screws. (fig 2a & 2b) The Controller Box has vents on either side of

the housing that allow the temperature and humidity sensors to work, so it is important to

locate the Controller Box with at least 1 inch of space between it and the underside of

the roof. (fig 3 & 4) For best results, locate the Controller Box near the fan opening as

shown. Mounting within 2 to 3 feet of the motor is recommended. (fig 5)

Standard Installation

4. Unplug the 2 wire leads (red and black) from the

motor. (fig 6) If your fan came with a thermal switch,

unplug the wire coming in from the solar panel to the

switch. (fig 7) The Controller Box will be replacing the

function of this switch. You will not need the thermal

switch and it can be discarded.

fig. 2b

fig. 2a

fig. 3

fig. 4

fig. 5

fig. 6

fig. 8

fig. 9

fig. 10

fig. 7

6. Take the other 8’ cable and connect the female leads to the solar connectors

on the Controller Box (red to red and black to black) and connect the male

leads into the female leads coming from the solar panel. (fig 10)

5. Take one 8’ cable (included) and plug the female leads into the motor (red to red and black to black) (fig 8) and

connect the male leads to the fan connectors on the Controller Box. (fig 9) Note: It is important to connect the

Controller Box to the motor BEFORE connecting to the solar panel.

WARNING: Fan will begin running as soon as sun hits the solar panel - keep fingers clear of the fan blades.