Installation – KROHNE OPTIMASS 2000 EN User Manual

Page 22

Advertising
background image

3

INSTALLATION

22

OPTIMASS 2000

www.krohne.com

10/2010 - 4000810002- MA OPTIMASS 2000 R02 en

Flexible connections can be used but because of the high flow rates associated with large
diameter meters, it is recommended that flexible connections are not used on meters larger
than size 80.

3.4.9 Hygienic installations

Where the meter has been approved by the sanitary requirements of the European Hygienic
Engineering and Design Group, you MUST give consideration to:

• Installation - install the meter at an angle to allow self-draining (see illustration).
• Cleaning fluids - cleaning fluids should flow uphill with a velocity rate greater than

1.5 m/s / 5ft/s. If the process flow is downhill, install a flow restrictor downstream of the
meter. This will make sure that the meter is completely filled with the cleaning fluid.

• Process connections and seals MUST be in accordance with EHEDG documentation.

The manufacturer also recommends that you refer to EHEDG (www.ehedg.org) document
number 8 "HYGIENIC EQUIPMENT DESIGN CRITERIA".

3.4.10 Heating and insulation

Heating

Heating

Heating

Heating

The meter can be heated by electrical tape (or similar) as shown. ONLY heat the meter in the
area marked A.

1 Install the meter at an angle to allow self-draining.
2 DO NOT install the meter horizontally.

MA_OPTIMASS2000_en_101022_4000810002_R02.book Page 22 Monday, November 22, 2010 5:47 PM