86037400 05/22/08

3-14

WINTERIZING YOUR UNIT


1. Shut off the water supply. Disconnect the water

inlet hose from the front of your console.


2. Connect all high pressure hoses and tools

that may have water in them.


3. Start the unit and turn water pump on. Open the

tool valve until water pressure drops and water
stops flowing.


4. Turn off water pump. Fill the water box with

approximately two gallons of 100% glycol base
anti-freeze.


5. Turn the solution pump switch ON.

6.
Open the tool valve until anti-freeze begins to

come out of the tool. Recover ALL anti-freeze
that comes out of the tools into an approved
container. We strongly recommend that you re-
cycle and re-use the anti-freeze.

Repeat this procedure with all the remaining
tools. After all tools and pressure hoses have
been filled with anti-freeze, disconnect and store
them.


7. Turn the solution pump switch OFF. Attach the

winterizing loop hose with attachment,
Part #86260700, PRV NO.10-805380, to the
solution outlet connection and the water inlet
connection. Turn the solution pump switch
ON.

Allow the unit to run for approximately 3 minutes
with the winterizing loop hose attached.

Open bypass valve and allow anti-freeze to flow
to waste tank.

8. Prime the chemical system with 50/50 anti-

freeze/water mix. Insert the chemical inlet and
prime discharge tubes into the anti-freeze
container. Turn the chemical valve to PRIME
until anti-freeze begins to flow out of the prime
hose.


9. Now turn the chemical valve to the open

position, making certain that the flow meter
indicates flow and that all anti-freeze drains out
of the chemical hose into an approved container,
after 30 seconds, turn off both valves.

When disposing of used anti-freeze, observe
local laws and regulations. Do not drain onto
the ground or into storm drainage systems.